Worked allowance example

The $3,000 allowance that added $4,057.

An allowance is not the final cost of a selection. This constructed tile example follows the full written cost stack—product, tax, delivery, added labor, markup, and the original allowance—so the contract change can be checked before approval.

Original HomeScope exampleFree 4-page worksheetIllustrative—not a price benchmark
THE RULE

Compare the final selection package to what the signed allowance actually covers.

The allowance might cover product only—or product, tax, delivery, and labor. Markup might apply to the full selection, only the overage, or not at all. A credit may follow a different rule. The written agreement controls; the example below states every assumption instead of hiding it.

Illustrative cost stack: a $3,000 tile allowance leads to a $4,057.20 contract increase and a revised project total of $76,057.20.
Visual summary

The overage is not simply $4,800 minus $3,000. The applicable tax, delivery, added labor, markup base, and credit rule must be written down first.

One signed project, one later selection

The signed total is $72,000. Then the tile is selected.

SIGNED PROJECT TOTAL$72,000Before the tile selection is finalized
TILE ALLOWANCE$3,000Assumed here to cover product only
SELECTED PRODUCT$4,800Before tax, delivery, labor, and markup

This is a constructed educational example—not an observed bid, Michigan cost average, legal interpretation, or recommended markup. The 6% tax line illustrates Michigan’s current general sales-tax rate; the taxable amount and contractor treatment depend on the actual transaction.

Selected tile$4,800.00The actual product selection
Illustrative 6% tax+ $288.00Applied here only to the product
Delivery+ $240.00Separately stated in this example
Added installation labor+ $1,200.00More layout and cutting than the base assumption
Selection package$6,528.00Product + tax + delivery + added labor
Less signed allowance− $3,000.00The product allowance already carried in the contract
Pre-markup overage$3,528.00The difference before markup
15% contract markup+ $529.20Illustrative markup on the pre-markup overage
WRITTEN CONTRACT INCREASE$4,057.20

$3,528.00 pre-markup overage + $529.20 markup

REVISED SIGNED TOTAL$76,057.20

The other direction matters too

A lower selection may create a credit—if the contract says how.

Suppose the selected product is $2,400, illustrative tax is $144, delivery is $100, and no added labor is required. The package is $2,644: $356 below the $3,000 allowance. That is only a theoretical credit before the written credit and markup rules are applied.

Before approving the selection

Seven lines that should be unambiguous.

01

Allowance basis

What exact product, quantity, unit price, tax, freight, waste, and labor does the allowance include?

02

Selection evidence

What vendor quote, order, or invoice supports the selection cost?

03

Tax treatment

Which amount is taxed, by whom, and where is it shown?

04

Delivery and handling

Are freight, delivery, storage, and handling included or added?

05

Labor effect

Does the selection change preparation, layout, installation, equipment, or schedule?

06

Markup formula

What percentage applies, and to which subtotal?

07

Credit rule

How is an underrun calculated, approved, and returned in the payment schedule?

Michigan Treasury states that the general sales-tax rate is 6% for taxable retail sales of tangible personal property. It also explains that contractors can be treated as consumers of materials used to improve real estate. This guide does not determine the tax treatment of a specific contract. Read the official Michigan source ↗

Portable selection record

Approve the arithmetic—not a surprise total.

The four-page PDF captures the signed allowance terms, selection evidence, full overage or credit formula, three-option comparison, and dated approval record. Use the same structure for cabinets, fixtures, flooring, appliances, hardware, or any other allowance.

Make the change visible

Calculate the selection before approving it.

Recreate the allowance, tax, delivery, labor, markup, and credit arithmetic from the written terms.